First part of repairs to the Valdai-Pleskava gas pipeline completed ahead of schedule
Gazprom has completed ahead of schedule the planned repairs to the transmission system on the Valdai - Pskov gas pipeline, which were scheduled to be completed by 6 February 2022.
The gas supply to the pipeline will be restored as early as 1 February 2022.
As a reminder, the second stage of the planned repairs will take place from 24 February to 7 April 2022. During the repairs, Gazprom will replace sections of the pipeline to improve the safety of the transmission system. The replacement of the transmission sections is carried out in accordance with the results of Gazprom's internal diagnostics.